Hi,

Would you advise the definition of the "Not Planned Work" in planning report? Thanks.

 

Rainbow


 
Posted : 04 Mar 2021 13H21
(@babynus)
Posts: 14952
Member Admin
 

It is the part of work that could not be planned due to unresolvable availability constraints.

For instance :

  • resource has 5 days left on Activity A, but will leave project in 3 days (allocation end date defined). Then you'll have 2 days of "not planned work"
  • resource is planned 0.5 day on a meeting day X, but entered holidays this day. Then you'll have 0.5 days of "not planned work"

 
Posted : 06 Mar 2021 13H25