Forum

Report to include a...
 
Notifications
Retirer tout

Report to include all(Validates,Planned and Real dates) for a project

10 Posts
3 Utilisateurs
0 Reactions
3,442 Vu
(@navver1990)
Posts: 49
Active Member
Début du sujet
 
[#7632]

Hello all,

Is there any report which can show all the details(Validated,Planned and real dates)for project and 
its activities.

Thanks,
Naveen


 
Posté : 16 Juil PM 14:077
(@babynus)
Posts: 14952
Membre Admin
 

The Gantt Chart.

Note that Gantt chart as Report will show same columns as the ons you select on Gantt chart screen


 
Posté : 16 Juil PM 16:077
(@alain-fourastie)
Posts: 366
Membre Moderator
 

Of course yes !
Have a look into report / planning.
or you can use filters on lists of projects with your values requested.
We also develop dashboards and reports on demand....


 
Posté : 16 Juil PM 16:077
(@navver1990)
Posts: 49
Active Member
Début du sujet
 

Hello,

Please find the attached Gantt report generated by me.I have selected all the field but still in that validated(baseline) start and end date is missing.How to put that in report.

Thanks,
Naveen 


 
Posté : 17 Juil AM 07:077
(@navver1990)
Posts: 49
Active Member
Début du sujet
 

How you develop reports on demand


 
Posté : 17 Juil AM 08:077
(@babynus)
Posts: 14952
Membre Admin
 

I think position of slider is also taken into account.
It means of you seen only 5 colomns on Gantt Chart, only these 5 visibile columns will be exported or report.


 
Posté : 19 Juil PM 12:077
(@navver1990)
Posts: 49
Active Member
Début du sujet
 

That is Okay,but my question is regarding the inclusion of baseline start and end date in the report apart from planned start and end date.


 
Posté : 20 Juil AM 08:077
(@babynus)
Posts: 14952
Membre Admin
 

You may mean "'validated start date" and "validated end date", that you can add on Gantt table (use columns selector button)


 
Posté : 20 Juil PM 14:077
(@navver1990)
Posts: 49
Active Member
Début du sujet
 

Hello,
In the Column selector table in the Gantt chart,there is nothing for validated start and end date ,only selection is there for planned start and end date.How to include now those dates for my reports generation.


 
Posté : 22 Juil AM 10:077
(@babynus)
Posts: 14952
Membre Admin
 

Yes, you're right.
IOn fact what you try to do is not possible.

Only option : save baseline and export PDF from Gantt Screen with baseline


 
Posté : 22 Juil PM 12:077
Share:
Retour en haut