Notifications
Retirer tout
Ask questions
2
Posts
2
Utilisateurs
0
Reactions
1,470
Vu
Début du sujet
Hi Team,
Is it possible to extract a report where I can see initially assigned work for each resource per project. So I can see a difference between assigned work and real work for each resource. Moreover, we also checked all available reports and have found only the reports where we can see real work performed by a resource.
Thank you.
Tatiana
Posté : 9 Déc AM 05:1212
I'm not sure such a report exist.
But what you want is displayed on the "Resource planning" view.
Posté : 15 Déc PM 14:1212

