Reports : How to get the "over worked" per ressource and per month?

4 Posts
2 Utilisateurs
0 Reactions
4,191 Vu
Kitcat711
(@kitcat711)
Posts: 65
Active Member
Début du sujet
 
[#4754]

Hello,

I am asking my team to put their real work and broacast the "Detailed work per resource - monthly" report.
One of our board member is asking wisely "How do we identify how good we are in forecasting ? and how do we detect underground problems?"

To illustrate: for one activity I planned "5 days" for a ressource, the "real work" entered is "12 days".
On the "Detailed work per resource - monthly" report I have no trace of the planned work.
I generated the others planning, real work and KPI reports with no success.

How can we get the synthesis, per ressource and per activity, for one month, between the "planned" work and the real "work"?

Kitcat711


 
Posté : 3 Nov PM 12:1111
(@babynus)
Posts: 14952
Membre Admin
 

We don't have this kinfd of report "per resource".
We are designeing new report (on V6.5) to calculate resource efficiency (on tichets and activity) but not sure this will bring you the detail level you expect.


 
Posté : 5 Nov AM 02:1111
Kitcat711
(@kitcat711)
Posts: 65
Active Member
Début du sujet
 

Hello,

OK, and do we have a way to create "our own reports"?
Kitcat711


 
Posté : 5 Nov PM 12:1111
(@babynus)
Posts: 14952
Membre Admin
 

OK, and do we have a way to create "our own reports"?

No, not through ProjeQtOr.


 
Posté : 5 Nov PM 21:1111