Hello here,
I have a resource (me) assigned to a project.
This project contains activities on which this resource is assigned on.
The planning calculator does not calculate the duration correctly ; the activity is displayed inside planning per resource but with no duration for these activities.
When I look at the project planning, it does display the activity but for the day of today and with a duration of 1 day.
Screens below :
Affections of the resource "not working" :
Affectation of the differents resources on the project
Planning of the resource "not working"
Project planning
Example of an activity on which resource is affected on
Best regards,
Jordan
Hi,
Check capacity of the resource.
If capacity is zero, planning won't work.