Hello
I have two question regarding recources capacity
- Is it possible define two diferent action ( work ) for the one resourcess in the same time
- Is it possible make for such condition ( ex. for three diferent resources , wiht diferent assigned day )
resources 1 - 40 day
resources 2 - 5 day
resources 3 - 2 day
normaly program make calculation " planed duration day's 47 day " - is possible make only planed duration as longest time needed ( resources 2 / resources 3 - make job pararell )
best regards