Hello,
I have an activity which begins and finishes the same day. I don't know why I receive for the due date the alert "respect of validated date". Does it due to the indicator configuration ? Thanks in advance for your return.
Best regards
If is because planned end date is over validated end date
Please show detail of alert.
It may be an alert than is no longer valid, but it's been raised and cannot be removed as an alert : please show whole activity screen.
So you have 3 "alerts" raised.
Last ones (57,58) are "alert" level, but not valid any more.
First one (55) is "warning" level, and still valid : you can see orange indicator on top left detail of item.
All seems correct.