(@florian_apside)
Posts: 7
Active Member
Topic starter
 
[#7731]

Hello,My problem when I have activities <1 day, the management of projeqtor does not seem correct to me.

Indeed if I have 2 activities of 0.5 days I would expect these 2 activities to end at the end of one day, but under projeqtor ends during the second day.

Do you have a solution?

Thanks,
Florian


 
Posted : 01 Sep 2021 15H25
babynus
(@babynus)
Posts: 14957
Main Contributor Admin
 

This happens if you add dependency between tasks.
Defautl dependency mode is "strict", meaning that if predecessor end day D, successor will start at D+1
You can change this behavior in global parameters.


 
Posted : 01 Sep 2021 16H19