[SOLVED] Assign Resource to multiple Activities

2 Posts
2 Users
0 Reactions
2,528 Views
(@iconic)
Posts: 280
Active Member
Topic starter
 
[#6909]

Is there a way to assign a resource as an assignment to multiple activities at one. I have about 100 activities and I have replaced one of my staff and I would like to assign the new staff as an assignment to the 100 activities of the person that I fired. How do I do this instead of using the assignment feature on each individual activity.


 
Posted : 08 Sep 2020 13H48
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Best way is to use the replacement of allocation feature.
Go to project, in allocation list click on "replace" button (withj two arrows crossing each other)
Then select new resource that will replace old one.
All assignments to old resource will be replaced with assignments to new resource.

Magic ! B)


 