[SOLVED] assign task

9 Posts
2 Users
0 Reactions
6,861 Views
(@yassine-bendadda)
Posts: 6
Active Member
Topic starter
 
[#3169]

is it possible to assign task to my ressource white hours not days and if one of my ressource don't do the task be reported to next day


 
Posted : 16 Mar 2016 22H05
(@babynus)
Posts: 14952
Member Admin
 

I don't understand.
Could you please explain ?


 
Posted : 16 Mar 2016 22H06
(@yassine-bendadda)
Posts: 6
Active Member
Topic starter
 

is it possible to assign activité by hours

and if activité not done be ported to next day


 
Posted : 17 Mar 2016 12H06
(@babynus)
Posts: 14952
Member Admin
 

is it possible to assign activité by hours

Change unit in Global parameters

and if activité not done be ported to next day

Just re-calculate planning.


 
Posted : 17 Mar 2016 19H45
(@yassine-bendadda)
Posts: 6
Active Member
Topic starter
 

portation is manually ?


 
Posted : 17 Mar 2016 19H52
(@babynus)
Posts: 14952
Member Admin
 

What is "portation" ?


 
Posted : 17 Mar 2016 20H12
(@yassine-bendadda)
Posts: 6
Active Member
Topic starter
 

importation d'activité ce fait manuel ?


 
Posted : 17 Mar 2016 20H14
(@yassine-bendadda)
Posts: 6
Active Member
Topic starter
 

importation d'activé se fait manual ou automatique


 
Posted : 17 Mar 2016 20H17
(@babynus)
Posts: 14952
Member Admin
 

Import of activity can be done throught Import feature (manually)
or you can deposit a correctly formatted Activity file in the folder defined as Import forder in the Global parameters screen.


 
Posted : 17 Mar 2016 20H17