Hello,

How can I change the number of days of my project when it has already been started?


 
Posté : 30 Jan PM 13:011
(@babynus)
Posts: 14952
Membre Admin
 

Validated Work is readonly not because project is started, but because value in consolidated from sub-items (tasks).
Check consolidation mode defined on global parameters (user manual may help to understand of the 3 modes)


 
Posté : 30 Jan PM 14:011
(@unluckyduck)
Posts: 10
Active Member
Début du sujet
 

Thank you for your quick reply, i'm looking at this right now


 