Hello,

At the today's training, you show us about "Administrative project" to manage vacation, sickness, training. So I create that project and it works well.
Now I would like to move this project at the top of the list (WBS 1) so that it will be at the top of the timesheet. As this project is not present in the planning view, I can't drag and drop it at the top.
Is there a way in the project list to change the WBS ?

Keep up the good job 😉

Regards.


--
Bena

 
Posted : 19 Oct 2018 0H01
(@alain-fourastie)
Posts: 366
Member Moderator
 

Hi
You have just to change the type of the administrative project into a type of an operational project, then perform a drag and down to the top, and re-type it into administrative code.

bye


 
Posted : 19 Oct 2018 11H23
Bena
 Bena
(@bena)
Posts: 65
Active Member
Topic starter
 

Nice 🙂

Many thanks !


--