[SOLVED] Date of Project and Activities

6 Posts
3 Users
0 Reactions
4,613 Views
(@pavilonsxx)
Posts: 58
Active Member
Topic starter
 
[#3284]

I have a question about the start and end of the project.
For example, I have a project ABCD with a start is 04/15/2016 and the project's end date is 04/30/2016.
The reason is that the activity of the project must be included in that period. But I can make the activity has a start date and an end date of 25/05/2016 and 05/30/2016. Thanks admin help explain?
Thank you very much.


 
Posted : 15 Apr 2016 11H40
(@richard-pare)
Posts: 165
Active Member
 

I have a project ABCD with a start is 04/15/2016 and the project's end date is 04/30/2016.

But I can make the activity has a start date and an end date of 25/05/2016 and 05/30/2016.

These dates are validated or planned dates?


 
Posted : 15 Apr 2016 16H19
(@pavilonsxx)
Posts: 58
Active Member
Topic starter
 

Yes, projects have validated. But I do not know how to planned, because it is not for the manually enter


 
Posted : 15 Apr 2016 20H21
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Validated dates are the commitments you wish to respect.
Validate dates on project put no constraints on activities.
It works the other way roud : it is activities that will determine start and end dates of project.


 
Posted : 17 Apr 2016 20H23
(@pavilonsxx)
Posts: 58
Active Member
Topic starter
 

As Ad said, the day of activity used to determine the start and end of the project.On my project, I set the start date and end date is 04/01/2016 04/20/2016. So my activities can make out the end of the project, ie I can create activities with a start and end date is 05/05/2016 05/20/2016. Meanwhile, my project end date will depend on the closing date of the last activity? Is it right?
There's something I do not understand much. 🙁
I think the day of the activities will be in the start date and end date of the project rather.
Thanks for the help 🙁


 
Posted : 18 Apr 2016 19H02
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

my project end date will depend on the closing date of the last activity? Is it right?

Yes

I think the day of the activities will be in the start date and end date of the project rather.

No, valiaded start-end dates are just what you expect (or wish, or committed to). IT is the activities, with work, constraints, that will determine dates for project.


 
Posted : 19 Apr 2016 2H48