Hello,
could you please explain the "fix planning" option in the project view?
In the manual it says "Fix planning Selector to fix the planning of the project, and its sub-projects."
but what does actually do and when is used.
Thank you
Marko
If you check this option, planning will be "protected" for this project.
This means that if you run planning for all projects or for parent project, the planning for this project won't be changed.
Right, thanks. I was interpreting the fix as an action that will fix (repair) something in the project.
The fix term is a bit confusing, but thanks all is clear now.