Hi,

1) I loaded the HR module which automatically created an administrative project called : "PROJECT - LEAVE PERIODE".
2) Then I created Absence type like explained here : https://www.projeqtor.org/files/ProjeQtOr%20-%20Documentation%20-%20Absences%20r%C3%A9glement%C3%A9es.pdf
3) I created acitivities for each type of leave.
Everything work well.

However, when I go to the Timesheet panel, the automatically created "PROJECT - LEAVE PERIODE" does not appear.
So finaly, when using HR modules, we could not use Timesheet directly with activities (RTT, CP...) created in the HR module.
The only way I found was to create another Administrative project, and create again new activities like RTT, CP. But then in the timesheet, dual leave period appears and does not make sense for user.

Is it possible to link activities defining leave periode from the HR module to the Timesheet?
Actually, why is the automacally created project from HR module not detected in the Timesheet panel ?

Many thanks and a great job was done with Projeqtor !

 


 
Posté : 30 Déc PM 15:1212
(@babynus)
Posts: 14952
Membre Admin
 

So finaly, when using HR modules, we could not use Timesheet directly with activities (RTT, CP...) created in the HR module.

No, this is the "old way", without HR Module.
With HR module, you must create leave periods through the HR screens (leave periods, calendar)

The only way I found was to create another Administrative project, and create again new activities like RTT, CP. But then in the timesheet, dual leave period appears and does not make sense for user.

Yes, both systems exist to enter leaves : "old one", simple, without validation process, "HR module", more complex to setup butr calculating leave rights and with validation process
Both systems should not be used, you should select one.
 

Is it possible to link activities defining leave periode from the HR module to the Timesheet?

No, they will appear when leave periods are defined.

Actually, why is the automacally created project from HR module not detected in the Timesheet panel ?

See above.


 
Posté : 4 Jan AM 10:011
 Wx
(@projwx)
Posts: 8
Active Member
Début du sujet
 

Many thanks Babynus for your very clear answer !


 
Posté : 6 Jan PM 16:011