Hello,
I noticed that the percentage of milestones is always either 0% or 100%!
is that there's way of having a percentage of 25%, 50%, 33%
thank you
Yes,
a milestone have no work, so it is just "no reached" or "reached".
There is no prgress on milestone.
The progress must be read on activities preceding (or generating) the milestone.
Thank you Babynus
is that there's way of having a percentage of 25%, 50%, 33% in activities progress ?
Of course : progress is [real work] / ( [real work] +
)
So it can take any value beetwen 0% and 100%
Its not working for me
I introduced two dates with a fixed duration planning, status in progress,
but progress still does not change 0%.
Can you please help me to set it or can you send me an example ?
Thanks
Go to http://demo.projeqtor.org
Connect as manager/manager
View activities 501 or 477
Hello,
it's quite a time back, but I'm interesting in this "progress", too...
Unfortunatly the activities 501 or 477 are no more longer present,
ist there another activity or example, where I can "learn" that based on a solid example?
regards
You can have a llok at activities #75, #48
In fact, in activities list, look for any activity with progress >0 (and possibly <100)