Good morning,
I'm working with the new version 10.4.1. I saw that there is a new evolution that allows you to visualize the "timeline". When I select on the Gantt Planning (in the "Access to additional parameters" section) the maximum row nothing happens. Same thing if I select "hide timeline" or not.
What should I do to see this timeline? (I searched in the online manual but there is no additional information)
Thank you,
Best regards,
Thank you for this very quick answer ! I manage to do iit. (I just discover this new "right click on an activity" evolution thanks to you)