Hello, I've got a problem wto input real work allocation on a Projeqtor test database (and not on my base of production).

On the two environnements, I do the same things :
Creation of a project
Affection of 2 ressources on this project
Creation of 2 activities with affectation of a ressource (this ressource have a charge of 5 days)

And the problem is....
On my "Production Projeqtor", when I go to Allocation screen, for the ressource, I can see the activitie and ca input real work
On my "test projeqtor"...I can't :unsure:

I have probably modify something (a parameter ?). I have been looking for two days without success.
It is the same problem with my login profile or admin profile.

Can anybody help me ? 😉


Regards,
Damien
-----------------------------------------------
.
ProjeQtOr v12.1.0 - Apache v2.4.56 - MariaDB v10.4.28 - PHP v8.2.4
Plugins installed : PersonalizedTranslation 1.6 - ScreenCustomization 7.2

 
Posté : 7 Avr PM 12:044
(@richard-pare)
Posts: 165
Active Member
 

And the problem is....
On my "Production Projeqtor", when I go to Allocation screen, for the ressource, I can see the activitie and ca input real work
On my "test projeqtor"...I can't

First, check if you selected the timesheet for the resource in the week where activities are planned.

Do you execute planning calculation?

Second, check the status of activities. Filters can be apply according to status.

The following text come from the user documentation:

"The list displays the assigned tasks for the resource.
Only assigned tasks that meet the next criteria will be displayed.
Assigned tasks planned during this period.
Assigned tasks that meet the criteria of selected filters."

---------
"3 - Filters

Filters allow to define the list of assigned tasks displayed.

Show only current week meeting

  • Check this box to show only the tasks on meetings of the week.

Hide not handled items

  • Check this box to hide tasks not taken over.

Hide done items

  • Check this box to hide completed tasks.

Show closed items

  • Check this box to show closed tasks.

Note

Global parameter “Display only handled tasks”

If the value of the parameter is set to “Yes”, only tasks taken over (status “handled”) will be displayed.
The checkbox “Hide not handled items” will be hidden."


 
Posté : 7 Avr PM 16:044
Damien
(@dnaton)
Posts: 248
Active Member
Début du sujet
 

Note

Global parameter “Display only handled tasks”

If the value of the parameter is set to “Yes”, only tasks taken over (status “handled”) will be displayed.
The checkbox “Hide not handled items” will be hidden."

Thanks, it was the problem 🙂


Regards,
Damien
-----------------------------------------------
.
ProjeQtOr v12.1.0 - Apache v2.4.56 - MariaDB v10.4.28 - PHP v8.2.4