Hello,
My manager has deleted the absence management project that existed in projeQtOr at installation.
How can I recreate this project with all its functionalities?

How to create an administrative project?

Regard,


 
Posté : 24 Fév PM 21:022
(@babynus)
Posts: 14952
Membre Admin
 

I guess the module "HR - Absence" has been disabled.
Just re-enable it. 


 
Posté : 27 Fév PM 17:022
(@epc)
Posts: 8
Active Member
Début du sujet
 

Hello,

I have reactivated the module, indeed it was deactivated. 
And I have created an administrative project.

Thank you for your help.


 