Hello Dear Mr babyrus, Good time.
I am writing to ask about report part. Does the report part files (for example real work- work weekly) understand not to calculate an off day performed real work? for example if sunday a real work is allocated, reports- real work- work weekly does not calculate the performed job in off days? I do not know why, but saturday and sunday real work allocated are not regarded in calculations in my reports?
Do you have any idea how to fix this problem?
Thank you very much
I really don't know why you get this issue, but real work is always counted, whatever the day.
What is possible is that it is not counted on the expected week.
A week is considered from Monday to Sunday.
If you expect to start the week on saturday, work is not onthe expected week.