[SOLVED] Real End Date affectation

4 Posts
2 Users
0 Reactions
3,862 Views
 HEU
(@quantamedical)
Posts: 58
Active Member
Topic starter
 
[#4682]

Hello,

I don't understand why a task with work to do have a real end date in past, whereas planned date is in futur
In planning, on top, date in past is even showed

You could show a screen capture join

Thanks


 
Posted : 04 Oct 2017 19H00
babynus
(@babynus)
Posts: 14954
Main Contributor Admin
 

It is strange.
You should not have a real end date as you still have left work.

Which version of ProjeQtOr are you using ?
Do you remind how you got this ? (use case to reproduce)


 
Posted : 06 Oct 2017 11H34
 HEU
(@quantamedical)
Posts: 58
Active Member
Topic starter
 

Task were done (fait), then re-open (ré-ouvert), then current (en cours)
I use last version 6.4.1 of projeqtor

When i show that, i try to make a new back cycle, without any change
I have to modify directly in Db ?

Thanks


 
Posted : 06 Oct 2017 11H58
babynus
(@babynus)
Posts: 14954
Main Contributor Admin
 

I have to modify directly in Db ?

No, never update the db.
We'll fix this issue in patch V6.4.2 (Ticket #3020 recorded)


 
Posted : 08 Oct 2017 17H16