Projeqtor Ver 11.0.2

Hi,

I have created two task with two ressources.

The resources B is involved in both task.

He start the job on task 1 "Application Automate", and 4 weeks after started I would like to involded this guy on task 2 "FAT Armoire" during one day.

I don't understand why, the task 1 is not shifted to finish on 8 april instead 5 april.

The guy B, is involved on task 2 after finshed the job on task 1....

The priority of task 1 is 100 and task 2 is 1. For me the task 2 should be executed before task 1 for the guy B (All activities with the lowest priority value will potentially be scheduled first).

Something is wrong in my understanding of projeqtor calculation....

Some help will be appreciate...

Thank you.

Fred
 


 
Posté : 05/01/2024 2:52 pm
(@babynus)
Posts: 14952
Membre Admin
 

The planning mode will generate some priorities that are more important than priority.
For instance, fix duration tasks are planned before Asap.

Moreover, you defined dependencies (start-start) to this will put higher priority for predecessor.

To manage what you expect, just define second task as Manual Planning, and mark the days you want to plan for the resource 
 


 
Posté : 07/01/2024 9:18 pm
(@fad)
Posts: 46
Trusted Member
Début du sujet
 

Ok Thanks you Babynus, it's works fine !


 