Hello
I'm using version 9.5.1
I need to have the time assigned for each of my ressources on each activity and export this to a spreadsheet
In the report I can only have reports with the time assigend for a ressource on a project, but NOT on an activity
The "ressources planning" screen shows exactly what I want but it is not possible to export it to a spreadsheet format (print and pdf are the only options)
Is there a way to get what I need from projeqtor ?
regards
I'm using version 9.5.1
![]()
Latest version is V9.5.4
Is there a way to get what I need from projeqtor ?
I don't thing the exact report you expect
too bad
I think such a report would be useful (there are reports on the time assigned on projects but not on activities)
or at least the possibility to export to spreadsheet the "ressource planning" screen
do you know if it is on the product roadmap ? Or maybe i should create topic in the "proposed evolutions" part of this forum ?
Regards
Request recorded as Ticket #6241
Thank you / Merci
Hello
Ticket #6241 says that a new report has been created, but I can't find it : what is is name ? how can I access it ?
regards
OK, thanks