Hello,
When I create a task, or when I report times in the workseet, I must type days (0,5 = half a day).
We manage projects and maintenance, and we often need to type times hour by hour, or 15 minutes by 15 minutes.
As I France we have a base day length of 7 hours, it's very complicated to type 1 hour.
And it's simply impossible to type 15 minutes.
Is there a option to allow the user to type times using "hour" unit rather then "day" ?
Hi,
Yes it is possible.
GO to global parameter / WORK / UNITS FOR WORK ;
Please note that 7h 8h or 9H etc is considered as 1 at the end of the day.
Please note that Projeqtor is a tool for managing whole project(s) and not to follow to the minute small time running tasks.
Regards
Thank you Alain,