Hi,
Here the case...
My task must be finished at 31/12/2015 and I plan 2 days to do it.
I began 1 day in april.
Then, the task begins in april and stops in december, without any interruption.
How can I view the real activity (I don't work since april but the bar displayed is full for the half period between april and december, wich is false) ?
Thx.


 
Posté : 10 Août PM 19:088
(@babynus)
Posts: 14952
Membre Admin
 

Hi,

the bar displayed is full for the half period between april and december, wich is false

It is not "false" as the bar show start to end. It just does not show fractionning of the task.
There are some ways to show fractionning :
- on resource planning, if fractionning is from real to planned, it is displayed.
- on work reports : you'll see planded work in detail


 
Posté : 11 Août AM 11:088
 DEV
(@lee)
Posts: 57
Active Member
Début du sujet
 

View in learning stage...


 
Posté : 10 Jan PM 13:011
Share: