Welcome to ProjeQtOr new Forum. We migrated old forum to the new website.
You will find all your posts here, with your usual account.
Just one point : you’ll have to reinitialize your password. Use “Lost password” feature.
I Have created 1 adminstrative project to follow some real work like holidays or trainings, but on real work allocation screen, the project appears in the middle of other internal projects I have created.
I understand we can manage order of project for example on planning screen (just have to drag & drop).
But administrative project don't appear on this screen 🙁
Is there a way to fix administrative projects for example at the beginning of real work allocation screen? (even directly with SQL?).
Thanks.
Best way :
1) change type of project from administrative to any operational one (not template)
2) reorder project on the Gantt view or even better on the Project Portfolio view to put it on top of projects
3) change type of project back to administrative
Of course!!
Thanks