Hello team !
Is there any kind of view or report which could allow to have into single view/report the workload forecast for all the resources allocated to a given project/sub-project.
For example for the next 12 months, have a numeric values for all resources month by month.
Could be for example the "colored monthly ressource planning", but with numeric values instead of graph, being able to have on a per week ou per month detail in addition to a per day, and being able to display on the same table next 3, 6 or 12 month.
I finally found it :
Report -> Planning -> Work Plan.
Maybe some additional features could improve these reports, but this was what i searched for.
Thank you for your answer