Hi all
I have the case that one team is working only one week per month on Projects, how can I simulate these case on ProjeQtOr (if it is possible)?
Thanks
Posted : 25 Nov 2015 13H01
Define a specific calendar for this team and select this calendar for all team members.
Posted : 25 Nov 2015 13H04