Hi,

On the underligned task, my ressource has to work today on that. I force validated end date to today, bu even when launching new calcultaion, green bar still blocked on yesterday.

Please advise.


 
Posté : 14 Juin PM 14:066
jmmbb
(@jmmbb)
Posts: 561
Contributor
 

Hello,

does your ressource have free work time for yesterday ?
If timesheet isn't full, Projeqtor assume that ressource can have done work yesterday but no update real work...

Regards,


 
Posté : 18 Juin AM 11:066