Hi,
Is there any solution to facilitate task assignment ?
we can affect an entire team to a project but after that, we need to add the entire team manually to the task, one member at a time.
Can we assign team to a task or maybe copy all assignment of an other task to the current ?
Have a nice day
Seb
No, it's not possible as it is a very specific use case.
In most cases you will assing 1 ou 2 members of the team, not all.
Only known exception : meetings (team meeting for instance) : and it's possible to assign whole team to a meeting.