Hello
PQ: 9.5.5
We have TestSession documents having hunderds of TestCases connected (and in our normal case it can be even much more).
Particularly, there is TestSession having 810 test cases which we cannot even change status becasue looks like PQ try for long time and just gives up (no error).
What is the reason of so long processing TestSession documents ?
How to work with such large TestSession documents ?
I think you can change status, but cannot change to "closed" status, as this will "close" the Test Case Run items linked.
Exactly this is the case. I cannot "CLOSE" it. Other TestSessnions (smaller) can be closed.
Is this problem somehow improved in new version ?
Yes, this is fixed on V10.0.0
Ticket #5871
https://track.projeqtor.org/view/main.php?directAccess=true&objectClass=Ticket&objectId=5871