On a new installation, a hidden project "PROJECT - LEAVE PERIOD" is created in the "project" table.
Whatever I try to do, with "admin" user I can't see this project and use it in the "absences" screen.
What I tried :
- Changed "admin" to a resource, employee and leaves manager (checkboxes in the "resource" screen)
- Created a new leave type "Congé payé"
After this, I can see the project and activity in the "timesheet" screen.
But in the "absences" screen I stil get a message "Add some activities on some administrative projects".
I tried to read the documentation, but it explains how to use the module, not how to configure it...
Any suggestion to help me?
This project is for internal purpose only.
You cannot access it.
It is created when you activate the HR module