Work input possible even if activity not started yet

2 Posts
2 Users
0 Reactions
2,769 Views
(@fmartin)
Posts: 43
Active Member
Topic starter
 
[#6139]

Hi,

I would like to create some activities in advance, beginning 2020/01/01, ending 2020/12/31.

I would like to know if that's possible to hide that activity from work input tab as the beginning date hasn't been reached yet.

I've been trying multiple things, but I can keep on seeing it in the input tab and I can input working time on it without any warning whatsoever.

Some help would be really appreciated 😉

Best regards


 
Posted : 18 Jul 2019 20H22
(@babynus)
Posts: 14952
Member Admin
 

It is possible if you check "hide not handled items". Then if you let the activity it a status that is not handled, it won't be displayed on Timesheet.
Ohter solution, is to check "under construction" on project. Then all activities of the project will be hidden on Timesheet


 
Posted : 25 Jul 2019 11H38