Work unit

2 Posts
2 Users
0 Reactions
2,514 Views
(@ddelhoume)
Posts: 1
New Member
Topic starter
 
[#2673]

Hello,
is it possible to create a project and "count" tasks in terms of "unit of work"?

Example : I have a reccuring task (manage Infrastucture servers) with no limit in time. I want to log this type of activity :

"Last Monday i managed servers during 40% of the day, I've worked on six servers (50% of total servers)".

My "unit of work" here is the number of servers i managed.


 
Posted : 26 Oct 2015 13H21
babynus
(@babynus)
Posts: 14954
Main Contributor Admin
 

No, it's not posible.

Only known unit is time.
In your example, your task is 0,8 days of work and you did 50% = 0,4 day.


 
Posted : 26 Oct 2015 14H00