hi,
I use projeqtor since a few time and i have a question on the update cost of ressources in the project with information of the order.

From the order (table and file php is "command") when you save it, how is made the update the informations of fileds work and amount towards the project ?, which is or are the files and fonctions which are used ? (to see in the project, the table update is planningelement with "reftype" is project, and updated fileds are "valitedwork", "valitedcost" and "totalvalitedcost")

Thank a lot


 
Posté : 07/07/2015 1:42 pm
(@babynus)
Posts: 14952
Membre Admin
 

Hi,
Orders will not update Work or Cost.
Orders could posibly update project budget, but this is a non existing feature in ProjeQtOr.

But I think report "Project Dashbord" (in category Miscellaneous) will give you the synthesis view you're expecting.


 