Hi Babynus,
first let me thank you for the new version, which has important improvements for us.
Projector RIA is still best of breed. 🙂
You invented new value "expected", what is highly welcome. Please, could you add this value in reports "work synthesis"? Here it would improve this great reports.
Thanks,
Klaus
It will be interesting to have some information/description about this new value as well
Regards,
Evgueni
Hi Evgueni,
it's real work / validated work. This is needed, because nobody in company is allowed to overdraft approved (validated) work. Progress is real work / planned work.
Klaus
Hi Klaus,
Ticket #970 recorded.