Limit real work to 1 day per day

3 Posts
2 Users
0 Reactions
3,718 Views
jmmbb
(@jmmbb)
Posts: 561
Contributor
Topic starter
 
[#910]

Hello,

when editing real work, there is no limit in how many time you spent in a day.
hen, it is possible for ressource to write down 2, 5, 10 or more workday for a single day. 🙁

Is it possible to put a limit, for example capacity of the resource ? [edit : in fact, it will be better to be able to write 1 day per day or more if resource as higher capacity - if a team is define as resource for example - but 1 day per day for resource with less capacity because this resource work really all the day - but not every days !).

Then, it will be easiest to control how many time per day a resource spent on a project. 😉

Regards


 
Posted : 22 Jan 2013 23H11
(@babynus)
Posts: 14952
Member Admin
 

Hi,

V3.1 brings this control, based on capacity of the resource.
It is not blocking, because a resource can have extra work.
The control only hilights (in red background) sum for days where total of real work is more than resource capacity.
It comes with the new "submit" & "validate" functionalities on real work allocation.


 
Posted : 23 Jan 2013 11H49
jmmbb
(@jmmbb)
Posts: 561
Contributor
Topic starter
 

Great !

Thanks a lot !


 
Posted : 23 Jan 2013 12H02