Hello,
I am going to enumerate features that I did not find in your application and which would be an asset :
more important :
- a tree view (or something like that) in projects view (for clarity of projects/subprojects)
- organize activities, tickets and milestones per project (with a lot of projects and tasks, filters are not still very practical)
- warnings on overdue dates on a project view -> automatic rather
- warnings on overdue budget (or work about resources) on a project view -> automatic rather
- % done of activities (also in the activities view)
- a monthly detailed financial report with per kind of resources costs, external costs, remaining to produce
less important :
- non-project activities (for time sheet)
- holidays
- bank holidays
- sick-leaves
- % done of projects in projects view (there is always the global gantt but with a lot of projects it doesn't offer a fast sight of projects advancement)
It is about all that my employers look for (besides the features of project' now ria)
I hope that my suggestions will help you, and keep in mind that projects managers want a quick sight of their projects' situation 😉
Best regards,
stephane fr
- a tree view (or something like that) in projects view (for clarity of projects/subprojects
What do you mean ? What is Project View. In fact tree view exists in planning, real work input.
- organize activities, tickets and milestones per project (with a lot of projects and tasks, filters are not still very practical)
It is ! Each item is attached to a project. Just select one projet in the select combo list (top left) will automatically restrict view to items of this project (and its sub-project).
- warnings on overdue dates on a project view -> automatic rather
- warnings on overdue budget (or work about resources) on a project view -> automatic rather
Ticket exists (#189) . Completed with your request.
- % done of activities (also in the activities view)
Good idea : new ticket #382 registered.
- a monthly detailed financial report with per kind of resources costs, external costs, remaining to produce
new ticket #383 registered. If you can send a template (excel, image, ...) it would be usefull.
- non-project activities (for time sheet)
- holidays
- bank holidays
- sick-leaves
Easy to manage non project activities : just create a project "Out of Project". You can add sub-projects for holidays or manage them directly through activities.
- % done of projects in projects view (there is always the global gantt but with a lot of projects it doesn't offer a fast sight of projects advancement)
It is included in #382.
What do you mean ? What is Project View. In fact tree view exists in planning, real work input.
He means in Projects you should have a tree view like in Planning, which would make the list much more readable when you have a lot of sub-projects.
Sebastian
Request registered as Ticket #648.
Low priority.