Hi,
On the gantt chart and project planning, do you plan to add hour level?
It would be nice for day to day planning at hour level.
Regards,
Sebastien
No, it's not planned to have Gannt display at hour level.
Day to day planning at hour level is much to precise: to my own experience, you should not plan tasks > 0,5 day. You'd spend more time planningthan realizing.
To have a look at the day to day planned actitity, each resource can see in the "real work allocation screen" the planned work each day on earch activity.