Hello,
i have a ressource affected on 2 project. 100% on project A and 100% on project B.
On the planning by ressource, ressource work on project B during 3 days, then on project A during 10 days, then on project B during 3 days. It's ok, but on planning view the green line for project B is continue. Is it possible to draw a discontinued line when ressource don't work on a project ?
Best reagrd's
Is it possible to draw a discontinued line when ressource don't work on a project ?
No, it's not.
Gantt planning is based on JsGantt library, that only deals with start and end dates.
The library has been extended to also take into accound real start and real end dates, in completion to planned start and planned end dates.
So there may be 2 lines : one grey for real, one green (or red) for planned.
There is no simple way to split lines corresponding on work, day by day.
Today, planning display is yet very time consuming, and provides poor performance when displaying many lines (many activities). So there is no planned evolution in a way that could degrade performance still more.