Is it possible to plan the next evolution:
to move the requested and validated dates of activities by mouving the dates of project.
for exemple,
I mouve the date (requested ou validated) of project:
start date 15/10/2013 -> 15/11/2013
automatically for activities:
activity 1: start day 16/10/2013 -> 16/11/2013
activity 2: start day 18/10/2013 -> 18/11/2013
....
Some similar request already exists.
In fact it will not be able to "move" valdated dates just by moving project start date.
Which rule should be applied ? What about off days in the period, resources availability ?
So what is planned is to be able to define walidated dates from planned dates. Some kind of "save initial planning".