Hello,

For the first time I try to use activity expense to manage external costs coming through SAP.
On the demo system (v.12.0.1) I created a project (#12), an activity (#10) and an activity expense (#4), linked to the previous activity. Everything works fine except for the project

Some screenshots :
- Activity expense

- Activity, we can see that the activity expense is considered as an expense with the correct amount

- Project, as you can see the expense amount of the activity (= activity expense amount) is counted twice


For information, same problem on our test platform v.12.0.1, but it is OK on our production environnement with v.11.2.3