Hi,
I tried to use the advanced filters but I think I discover one issue:
For example, on the project tab, I want to create one filter with >= on work assigned is not working
All filters with >= are not working.
I'm using ProjeQtOr v5.1.4 on Linux.
Hi El Wallos,
I already tested it with V5.2.1 and it works well. Did you test it on demo version of this web site?
Klaus
Thanks climb4fun
I tried on the demo and it works fine but I understand, in my config, all works and real work allocation are working with hours but on the advanced filters, day is the unit. So, I wanted to check >= 1 (imo, it was on hours...) but no, it is on days. I changed my filter from >= 1 TO >= 0.1 and it works fine.
Perhaps, an evolution to take the global parameters (for works) on the filter.
You are right and I confirm, if unit is hours, then filter works still with days. If in your global parameters a day has eight hours, than you have to divide your filter value by 8 to make the filter working properly.
I support your delevopement request in this way.
Have a nice day.
Klaus
Ticket #1932 recorded.