I'm preparing new projects for 2015 based on existing projects that I'm trying to copy.
This is ok for almost all parameters except for "assigned costs" . These appear in the copied project even if no ressource are already defined for this project.
What could you suggest to solve that ?
Thanks in advance,
Add and Remove one assignment on the bottom most activity.
This will update data.