Hi !
I have a big problem with planification and planned date : I have 41 elements (activity and milestones) with planned end date before planned start date. I tried to modify it on database, and run automatic plannification, but the issue occurs again.
With this problem, I can't change anything on the element form.
Have you ever seen this before ?
Thank you by advance.
Cédric
With automatic calculation or manual calculation, it is the same...
Oh ... I will work on this anomaly and i will return to you
Have you got assigned work for your resource in assignment ?
No, not for this activity. Ressources for this element are external.
We have fixed this anomaly.
Fixed on next patch 6.2.5.
Great ! I'll test that very soon !
Thank you !