BUG - Can't update (or) change project affectation resources.

3 Posts
2 Users
0 Reactions
5,154 Views
(@stevanovich)
Posts: 4
Active Member
Topic starter
 
[#141]

Hi,
I woul'd like to change a % of project afffectation ressource (user), because i can't set this user to another project.
This user also use real work allocation .
When i change affectation of this user, in an activity , % inside activity is updated, but % inside project is not updated and seem to still locked to 100%
I can't delete this user from this activity (because of real work allocation ?).
So now i cannot set this user to another activity.

Hope i explain it correctly ... (i must improve my english 😉 )
Best regards.

Stéphan.


 
Posted : 19 Jul 2011 15H37
(@stevanovich)
Posts: 4
Active Member
Topic starter
 

Sorry,
I found what was the problem, not a bug !!!
I must unset or change the % of use in Affectation (Environnement)
After, i can now set this user to an other project.

I am glad to discover that i must set user affectation in environnement to be able to set user activity ....
Should'nt be better to be able directly assign user affectation in activity ?

Thanks


 
Posted : 19 Jul 2011 16H06
babynus
(@babynus)
Posts: 14955
Main Contributor Admin
 

Hi,

All of this is clerly eplained in the online manual (on Planning part) :

A resource has a capacity
Most of the time Capacity = 1 FTE (1 full time equivalent), but it may be more (if the resource is not a person but a team) or less (if the person work only partial time).

A resource is affected to a project, at a certain rate
If resources are not shared between projects, so rate will probably always be 100%.
But if resources are shared, then rate could be less than 100%. If a resource is equally shared between two projects, then each project should enter a rate of 50%. This will lead to control that planning for each project will not overtake rate capacity, so that first project planning its activity will not take all the availability of the resource.
Project affectation capacity is controlled on a weekly basis. This means that planning for a project (including sub-projects) will not be more than (Resource Capacity) x (Resource affectation rate) x 5 for a given week.

A resource is assigned to an activity, at a certain rate
By default, assignment rate is 100%. But it may be less. This means that planning will keep some availability for other tasks.
Assignment capacity is controlled on a daily basis. This means that planning for an activity will not be more than (Resource Capacity) x (Resource assignment rate) for a given day.

This is not the most simple way, but it is the most able to fit all needs.

Regards.