(@damien-gozillon)
Posts: 54
Active Member
Début du sujet
 
[#4477]

I created Default Projet or Model (Modele in French).
The problem is I cannot copy it. I have an error message (see attachement).
I put a date and charge in every task (it should'nt be necessary in a model anyway...) but I still have this message.
I tried to cha,ge the type of projet but I still have the mesage.
And I can't see where is the problem.
Can you please help me ?


 
Posté : 5 Juil PM 13:077
(@damien-gozillon)
Posts: 54
Active Member
Début du sujet
 

There was some task with a validated duration of 0. Wich is normal if the task is "planification" for example. So I solved my problem but there is still an issue. At least the error message should say where is the problem (which task).


 
Posté : 5 Juil PM 16:077
(@richard-pare)
Posts: 165
Active Member
 

This isn't an error.

You use the planning mode "Fixed duration" who forcing you to set the duration date.

If you want don't see the message anymore, change to a floating planning mode.

May be the "project template" feature can be improved for fixed planning modes.


 
Posté : 5 Juil PM 17:077
(@damien-gozillon)
Posts: 54
Active Member
Début du sujet
 

thanks for your answer.

I can set the planning mode on a task but I can see where you can set it on the project?
Because there was no error on tasks. Only on the project when I tried to copy it.


 
Posté : 5 Juil PM 17:077
(@babynus)
Posts: 14952
Membre Admin
 

I can set the planning mode on a task but I can see where you can set it on the project?

There is no planning mode on project, only on activity.

Because there was no error on tasks. Only on the project when I tried to copy it.

The error is on the task. What is weird is that you should have the error on the template...
Can you try and update every activity of the template to identify source ?


 
Posté : 7 Juil PM 18:077
(@damien-gozillon)
Posts: 54
Active Member
Début du sujet
 

I did another try and I have the same message. I refreshed everytask, replanified, and still no task in error. This time again I have a validated duration at zero, to planify as soon as possible, with a planified duration of 1 wheras the begin and end date are the same.


 
Posté : 8 Juil AM 02:077
(@damien-gozillon)
Posts: 54
Active Member
Début du sujet
 

Finaly it was another task with no duration validated (no mistake again, and it's normal). When I set one, I was able to copy.


 
Posté : 8 Juil AM 02:077