I think there is an issue on the total planned and available ... this is not in accordance to the display date... I think it's begin on the start of database...
in the following screen shot, I just take one year display date and its planned more than 5000 hours for one ETP ressource ???
Posté : 14/01/2025 12:37 pm
Yes,
We have issues with dates taken intpo account for planned and available, then average is false
We're working on the subject.
Posté : 14/01/2025 4:27 pm