meeting with or without left hours

6 Posts
3 Users
0 Reactions
932 Views
(@pdecloedt)
Posts: 166
Active Member
Topic starter
 
[#9561]

I've got a probleme, I'd change, on time sheet, the left of this meeting, but the left on progress section don't change and, I cannot close this meeting.

 


 
Posted : 02 Sep 2024 12H33
(@marylene)
Posts: 592
Contributor Admin
 

Hello,

Have you tried to directly change the status of the meeting by putting it on the last status of your workflow, which should be linked to an item closure?


 
Posted : 04 Sep 2024 12H29
(@pdecloedt)
Posts: 166
Active Member
Topic starter
 

 I just tr to put on workflow "Done"... same issue...

 


 
Posted : 04 Sep 2024 12H41
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Try and manually update Assignment table : add  1 assigned day (this will add 1 left day).
Remove the added day.
Left work should be recalculated


 
Posted : 05 Sep 2024 13H08
(@pdecloedt)
Posts: 166
Active Member
Topic starter
 

impossible to had some assignement hours...
I put in, mechanic wheel turn long time... and nothing change...
and nothing on the log file...


 
Posted : 05 Sep 2024 14H47
babynus
(@babynus)
Posts: 14966
Main Contributor Admin
 

Do you have errors in browser console ?


 
Posted : 17 Sep 2024 13H29