On meetings screen :
- I create a new meeting
- choose a date and hours (for example 19/05/2022 - 15pm to 16pm -> 1 hour meeting.
- Save
- Attendees -> Automatic assignment of the project team => Create one line per resource (ok), but in "assigned (h)" column -> put 7h per resource, instead of just 1h. (if 2 hours - meeting => 14h assigned by resource...)
I have not the problem while adding resources one by one.
Thanks a lot for your answer,
Best Regards,
Anaïs
This seems to be an issue when work is defined in hours.
(I guess you defined 7 hours per day)
Ticket #6205 recorded
I cannot reproduce.
Which version of Projeqtor are you using ?
We have updated this morning for v9.5.4.
I still have the problem and reproduce it every time.
What could I send to help ?
Thank you,
Anaïs
I have added some files :
- Global Parameters on work section
- Example : Create a meeting
- Juste add name and date (today - from 14pm to 15pm)
- Save the meeting
- Activate automatic assignement of the project team -> And automatically 7 hours are assigned per person.
Show configuration for Global Parameters in "Work" section.
Show step by step use case to create issue, with screenshot or video.
Hello Amaz,
after a software update, we sometimes faced such kind of «lack of update» for some update-related topics.
Even if it looks weird, have you tried to logout (I said logout, not killing the tab or the browser) then ctrl+F5 then login again ?
Hello,
I have tried but still have the issue.
Sorry !
Anaïs
Ticket #6205 reopened